Randall Avenue

 
 

Project Description

 

The Project consisted of mainly staged reinforced cast-in-place concrete bridge deck and barrier replacement of 2.2 miles, the two lane roadway of the Westbound NJ Turnpike Authority NB-HCE. In addition, lighting and drainage improvements were made and the approach pavement at Interchange 14C was replaced with precast panels during weekend-long work periods.

Key Elements

 
  • Monolithic reinforced concrete bridge deck removal
    and replacement (Approx. 480,000 SF)

  • Lighting improvements

  • Structural steel repairs

  • Bearing replacement and repairs

  • On-grade pavement replacement using pre-cast concrete panels

 

Other Data

 

Location  Jersey City, NJ

Contract type  design-bid –build

Owner  New Jersey turnpike authority

Designer  GPI Greenman Peterson, INC.

Value  $66.5M

Status  Completed March 2016

 

Lefferts

Let’s Build Together

We’re always looking for new opportunities and are comfortable
working internationally. Please get in touch and one of our project
managers will contact you about beginning the proposal process.